Step-by-step guide
- This will only be available and work for Super Users.
- Logon to the NRDA appliance and go to the Security section
- In this example we will move PEDW project under NRDA2 to be under ICODA
- Select Move Project from the menu bar at the top and select which project you want to move and which parent you want to move it to. In this case we select PEDW as the project we want to move and ICODA as the project we want to move it to
3. Click the Move Project button. So long as your move doesn't leave a gap in the tree or a loop you will get a success screen (if not you will be told the move can't be done).
4. You may need to wait upto two hours for provisioning to update the tree hierarchy.